1.0 Description


Procurement is an important function to ensure that UNDP meets its organizational goals. While Procurement is a support function for the organization, it is nevertheless a core function and critical to enhancing programme/project delivery. UNDP does not conduct procurement in isolation, but rather as part of the process of achieving development project outcomes. Therefore all UNDP procurement activities are framed in the context of UNDP programmes and projects.

Understanding procurement as a managerial discipline (and not an administrative one) implies the need to acquire and enhance certain managerial skills and tools, including:

  • Procurement Risk Management
  • Procurement Strategies Development
  • Procurement Planning

Understanding…

What do we procure?

(Spend Analysis) 

In which markets do we operate?

(Market Analysis)

What are the associated risks?

(External, internal, project risks)

We will develop…

Risk Procurement Management Procurement Strategies Procurement Plans

When we talk about procurement, is it necessary to broaden the concept to include Supply Chain Management (SCM), as procurement is one of the elements of the Supply Chain.

Management of the supply chain also includes:

  • Product selection
  • Forecasting or quantification
  • Procurement, including Quality Assurance
  • Inventory management, including Storage (if applicable)
  • Distribution (if applicable)
  • Return (if applicable)

As a working principle, we always need to take into consideration all steps of Supply Chain Management (SCM) when analyzing procurement risks, defining procurement strategies and planning.  The complexity and length of the supply chain will vary from project to project.

Supply Chain Management risk analysis, procurement strategies development and planning are essential tools to ensure that procurement activities support project outcomes, are conducted in a timely manner and at a reasonable cost. Early and accurate planning is critical to avoid last minute procurement, which is contrary to open, efficient and effective procurement.

When does (1) procurement risk analysis (2) procurement strategies and (3) procurement planning start?

SCM cycle is an integrated part of the project cycle, and therefore needs to be aligned and synchronized with other project activities in order to contribute to achieving identified outcomes. To this end, the SCM cycle cannot run in isolation. On the contrary, it must be integrated into the overall project cycle.

This implies by definition the need for a constant interaction between operations and programming.

In the project context, SCM risk assessment and procurement strategies development and planning should start as early as the project definition stage.

At this point, important questions will need to be addressed, including:

  • What will be the implementing modality? Who will be responsible for procuring and managing inputs?
  • What are the existing risks? Are there risks associated with the nature of the
  • products or services to be acquired? Are risks associated with the markets, the environment or the political context?
  • What is the best procurement strategy for achieving the programme/project goals and to mitigate risk?
  • What is the Procurement Plan and what are the associated resources?
  • What are the main acquisition activities to be conducted that will contribute to the identification of project outputs?  Among these activities, will there be acquisition of goods, services (professional or individual) or works?
  • What is the procurement and product expertise required to successfully conduct the identified procurement activities? Does it exist in house or do we need to outsource it? Does UNDP or the implementing partner have the capacity to develop specifications/TOR/SOW, or do we need to hire specialized experts? What about the evaluation?
  • What is the budget required to achieve the identified outcomes? All required activities, either goods to be procured (i.e., ballot boxes for an electoral project) or services (i.e., individual consultants to develop specifications) must be budgeted.

What are the benefits of this approach?

Together, procurement risk assessment, procurement strategies development and procurement planning serve as a bridge to cover the gap between programme and operations. They are also critical to programme delivery. Benefits of this approach include:

  • Best value for money
  • Timely procurement
  • Avoid unnecessary and unjustifiable emergencies
  • Better allocation of existing resources
  • Sufficient time to fully explore alternative procurement approaches
  • Possibility to aggregate demand

What are the success criteria?

  • Joint Planning between programme and procurement in the early stages
  • Good flow of communication
  • Understanding of the procurement requirements
  • Understanding of the market and associated risks
  • Live process with structured revisions and feedback mechanisms

TYPES OF PLANNING

  • Consolidated planning
  • Individual planning

Consolidated Planning

Based on the UNDP decentralized structure, consolidated procurement plans will be developed at different levels, including Corporate, Business Unit and Country Office.

All Business Units and Country Offices shall develop Consolidated Plans. They will normally be prepared annually, though it is a good practice to review them regularly.

Analysis of the consolidated Procurement Plan provides an opportunity to identify economies of scale and better uses of resources, providing an overview of the scale of the procurement activities.

Individual planning

Procurement planning will also take place at the project level or even at the activity level, depending on the complexity of the activity and the number of interrelated procurement actions.

A Requisition Plan shall be developed at the project definition stage. It must be shared with the Procurement Unit.

All “Significant Purchases” of a Requisition Plan (definition is provided in Section 4.2) are subject to the development of an Individual Procurement Plan.

Go to top

2.0 Relevant Policies


  • UNDP Fin. Rule 121.03(a) (May 2005)

Go to top

3.0 Flow Chart



There is no flowchart for this sub-process

Go to top

4.0 Procedures


As SCM (and procurement in general) is a sub-process of the project cycle, different actions will need to be taken at each stage of this cycle.

The UNDP Project Management Cycle includes the following steps:

  • Justifying the project
  • Defining the project
  • Initiating the project
  • Running the project
  • Closing the project

Below are some of the questions and issues that must be considered at different stages of the project.

Project CycleProcurement Cycle/SCMMain Documents
Justifying a project

N/A

N/A
Defining a project
  • Identify internal procurement resources
  • Identify external resources (if required)
  • Identify procurement risks and procurement strategies
  • Product/service selection or identification
  • Forecasting/Quantification
  • Budget
  • Identify SCM responsibilities
  • Assess SCM implementing partner capacities
  • Develop REQUISITION PLAN
  • Identify asset management strategy

PRODOC

PROCUREMENT RISK ASSESSMENT

PROCUREMENT STRATEGIES (including sourcing strategies)

REQUISITION PLAN

SUPPLY CHAIN MANAGEMENT PLAN (if applicable)

Initiating a project
  • Development of a TRANSACTIONAL PROCUREMENT PLAN
  • Develop Specifications/ TOR/SOW
TRANSACTIONAL PROCUREMENT PLAN
Running a project
  • Monitor and review Procurement Plan or the Procurement and Supply Management Plan
  • Source Suppliers
  • Select Suppliers
  • Award and Contracting
  • Monitor performance and manage contracts
  • Depending on the SCM obligations indentified during the definition of the project, UNDP will be responsible for storage, inventory management and distribution
MONITORING AND ADJUSTMENT OF THE TRANSACTIONAL PROCUREMENT PLAN/SUPPLY CHAIN MANAGEMENT PLAN
Closing a project
  • Close project
  • Dispose/transfer assets
  • Identify procurement lessons learned
.

Procurement Risk Assessment, Procurement Strategies Definition and Planning shall be integrated at the programming stage and not as a back-end process.

4.1 PROCUREMENT RISK ASSESSMENT AND RISK MANAGEMENT

UNDP needs to proactively and systematically monitor and manage risks (defined as both threats and opportunities). Among other risks, UNDP must identify and manage any risks associated with the conduct of its procurement activities. UNDP must not only be aware of and monitor the procurement risks it faces, but it must also proactively anticipate and assess those risks. This chapter deals exclusively with “transactional” procurement risks. Therefore it does not elaborate on Corporate Procurement risks, which are part of UNDP Corporate Procurement Strategies.

UNDP has adopted an Enterprise Risk Management strategy which provides the frame to deal with all risks, including procurement risks. For further information about ERM at

The Risk Management Cycle includes the following steps:

1. Risk IdentificationWhat are the key risks and opportunities?
2. Risk AssessmentHow does the potential impact relate to our risk tolerance? What is the likelihood of a risk event and what would be the impact?
3. Risk PrioritizationWhat are the most critical risk issues that demand our attention?
4. Taking ActionWhat is the best course of action? What are our strategies? How will we know that our mitigating actions are effective?
5. Monitoring and ReportingAre action plans being implemented? Are they effective in mitigating risk? How are we monitoring their implementation?

A number of procurement risks must be taken into consideration when defining procurement strategies. These can be clustered in three main groups:

  • Environmental risk, including the political environment, natural environment or delivery infrastructure environment, among others
  • Programme risk, including but not limited to the risk of operating in the market, the complexity of the Supply Chain Management, or the risk associated with the nature of the service or goods to be acquired, among others
  • Implementation risk, or risk associated with the implementation unit capacity

In the table below you will find some examples of potential risks and mitigation activities. Please note that this list is for reference purposes only and is not exhaustive.

RiskPossible ConsequencesPossible Solutions
Critical procurement activity

Failure to secure ongoing supply critical to the organization

(i.e., elections)

Failure to achieve key organizational results

Total costs of procurement too high

Develop market knowledge

Identify alternative sources and extra due diligences to check he capacity of suppliers

Plan in advanced

Work closely with beneficiary/ partner to be aware of rapid changes of needs

Apply contractual penalties and remedies

Selection of procurement Strategy
Selection of inappropriate procurement strategy

Inadequate or inappropriate results

Not achieving best value for money

Damage project implementation

Agree on desired outcomes/objectives and have a clear understanding of the project objectives

Develop a good understanding of associated risks in order to incorporate them into procurement strategies development

Planning
Lack of planning

Delay in project implementation

Inadequate supplier response

Procurement process shortcuts

Higher prices

Early involvement of procurement officers in project planning

Develop and communicate an accurate Requisition Plan

Insufficient lead-time

Inadequate supplier response

Procurement process shortcuts

Higher prices

Involve procurement officers in the project planning phase
Delay requisitions to create false emergencies

Claims of unethical or unfair dealings

Delay of project implementation

Higher total cost of acquisition

Not achieving Best Value for Money

Early involvement of procurement officers in project implementation

Seek proper justification of emergencies

Training of requisitioners

Requirements definition
Restrictive specifications/TOR/SOW

Claims of unethical or unfair dealings

Inadequate suppliers response

Limits competition

Unfair treatment of suppliers

Lack of transparency

Developed market and product understanding

Include generic functional and performance specifications

Apply relevant international standards where applicable

Inadequate specifications/TOR/SOW

Significant variety in offers received

Insufficient responses

Offer of goods/services that do not meet needs

Difficulty in evaluating competing offers

Become familiar with requirements of the specification/TOR/SOW

Developed market and product understanding

External support (consultant) to developed specifications/TOR/ SOW linked to clear deliverables and target time

Do not include quality requirements in specifications/TOR/SOW

Impossibility to achieve best value for money

Difficulty in comparison and overall evaluation

Poor quality of the procured items, which may lead to a waste of funds

Include quality in the specifications/TOR/SOW, using international and national standards

If quality is a critical issue, extra due diligence must be used (i.e.,  check manufacturing process and standards, factory visits, sampling and independent laboratory analysis, pre-shipment inspection, etc.)

Sourcing
Wrong approach to market

Inadequate or inappropriate supplier response

Higher prices

Selection of inappropriate approach

Analyze supply market

Develop sourcing strategies

Identify wrong sourcing strategy or do not have sourcing strategy

Inadequate or inappropriate supplier response

Limit competition

Proper application of the pre-qualification or post-qualification, depending on the identified complexity and risk
Misrepresentation of facts by potential suppliers

Contract with unsuitable companies

Claims of unethical or unfair dealing

Breach of contract

Independently verify suppliers’ qualifications

Conduct supplier reference check and due diligences

Outdated information on potential suppliers

Inadequate suppliers response

Limit competition

Maintain suppliers roster
Advertisement of procurement notices in inappropriate media

Lack of sourcing strategy

Limit competition

Contract with unsuitable companies

Identify relevant media to post procurement notices
Preparation and issuance of solicitation documents
Use of inappropriate evaluation criteria

Inadequate or inappropriate results

Not achieving best value for money

Re-tendering (time/ cost)

Have clear goal to be achieved as a result of the procurement process

Consider implications of evaluation criteria

Unacceptable requirements to suppliers

Loading the cost in offers

Limits competition

Too few bids

Re-tendering (time/cost)

Develop strong understanding of market and industry practices

Develop commercially acceptable terms

Check that responsibility for risks is not allocated to suppliers for factors outside their control

Provisions of inadequate information

Loading cost in offers

Great variation in offers

Create confusion among potential suppliers

Re-tendering (time/cost)

Review documents before issue

Know the market

Receipt and Evaluation
Failure to observe effective evaluation procedures

Lack of fair treatment of suppliers

Inconsistency in evaluation of offers

Subjectivity in outcome of the evaluations

Composition of the evaluation team in line with the project scope and complexities

For high tech/highly complex procurement activities, ensure technical expertise

Ensure staff are suitably trained and experienced

Failure of offers to meet project needsNeed to re-tender

Ensure that specifications are understandable, generic, and in line with what exists in the market

Know the marketplace

Failure of evaluation to identify a clear winner, leading to subjective discussions or development of “new criteria”

Claims of unethical and unfair behavior

Need to re-tender

Ensure that selection criteria are appropriate and aligned with the project needs
Selection of inappropriate supplier

Failure of the supplier to fulfill the contract

Waste of funds

Contract disputes

Re-tendering (time/cost)

Reject offers from unacceptable suppliers and document rationale for the rejection

Develop clear evaluation criteria aligned with the project needs

Perform technical and financial checks on suppliers before awarding the contract

Select inappropriate goods/ service

Failure of goods/services to meet the project needs

Waste of funds

Re-tendering (time/cost)

Develop proper specifications/ TOR/SOW

Have the right technical expertise during the evaluation process

Ensure users are involved

Insufficient number of responses

Need to start the procurement again

Delays to procurement schedule

Lack of value for money due to limited competition

Develop strong understanding of market

Foster international competition

Develop supplier rosters

Allow for sufficient time for suppliers to prepare offers

Procurement Review and Award
Contract approval not obtained

Delay in the contract award

Need to re-bid (time/cost)

Undermine business community trust

Proper procurement risk analysis

Proper procurement strategies (including sourcing strategies)

Market understanding

Proper procurement planning

Clear, generic and complete specifications/TOR/ SOW

Foster international competition

Ensure adherence throughout process to rules, regulations and procedures

Ensure adequate documentation of process and submission

Contract management
Unstructured or nonexistent  contract management function

Not achieving best value for money

Poor performance of suppliers

Delivery delays

Possible cost variation

Contract disputes

Identify resources for contract managements

Develop structures for contract management, including clear roles and responsibilities

Identify the right profile and competences for contract management

Develop contract management plans

Failure by either party to fulfill the conditions of the contract

Contract disputes

Failure or partial failure to satisfy the project needs

Delays

Legal actions

Ensure proper contract management

Contract monitoring, including regular inspections and progress reports

Review past performance records

Be proactive

Maintain accurate records and documentations

4.2 DEFINITION OF TRANSACTIONAL PROCUREMENT STRATEGIES

First and foremost, any procurement activity needs to be aligned with the UNDP Strategic Plan. Please familiarize yourself with the Strategic Plan by visiting http://intra.undp.org/results/strategic_plan.shtml.

Based on the information gathered, potential buying strategies should be identified and evaluated.

All procurement activities require procurement strategies. However, activities designated as “significant purchases” will require special attention.

We can define significant purchases as those that are of high relative expenditure and/or for which supply is difficult to secure.

The relative expenditure of goods and services is defined as their cost relative to the total purchasing expenditure of the business unit or agency. For UNDP, a transaction of 100,000 USD or more is considered a significant purchase.

The criterion “difficult to secure supply” will be based on the following factors:

  • The degree to which the goods or services being purchased present a risk or are critical to the agency; as well as
  • The extent to which there exists a competitive market

Significant purchases are:

  • High in relative expenditure and easy to ensure supply
  • Low in relative expenditure and difficult to secure supply; and
  • High in relative expenditure and difficult to secure supply

Based on the information gathered, an understanding of the nature of the procurement activities, a knowledge of the market and an understanding of existing risks, UNDP will develop unique procurement strategies for each project. Potential strategies include:

  • A purchase high in relative expenditure and easy to ensure supply may require a strategy with the aim to ensure that total cost (including the cost of processing large numbers of low value transactions) are reduced (i.e., demand aggregation).
  • A purchase low in relative expenditure and difficult to secure supply may require a strategy seeking to ensure an ongoing supply, in order to reduce exposure (i.e., carrying an emergency stock or developing alternative sources of supply).
  • A purchase high in relative expenditure and difficult to secure supply may require special supplier relationship management.

Procurement strategies will seek to meet identified project goals and to mitigate existing risks. For example, in the case of a procurement transaction where quality is critical, UNDP procurement strategies will not only include clear specifications reflecting national and international standards, but could also include supplier pre-qualifications, factory visit(s), sampling and independent laboratory testing, or pre-shipment inspection, among other actions.

In the case of a project were delivery is critical (i.e., elections), potential strategies could include early ordering (if proper planning has been conducted), pre-qualification of suppliers (to ensure that with all  suppliers being considered are reputable and capable), developing alternative sources, checking manufacturing capacity, requesting performance security and including extra assurances in the contract as liquidate damages clauses, among others.

4.3 PROCUREMENT PLANNING

Procurement planning entails more than the selection of a procurement method for various goods, civil works and services or when to schedule activities. It is highly dependent the legal and institutional frameworks in which procurement must be carried out.

REQUISTION PLAN

During the definition stage of the project cycle, all relevant activities will need to be identified and budgeted. Among these activities, considerations must be taken for the acquisition of goods, services and works in order to achieve the project objectives.  Required services identified should also include any individual consultant services necessary for the successful implementation of the project (including services for complex/highly technical specifications development, if applicable). This information will be the groundwork for the establishment of the Requisition Plan.

The Requisition Plan shall be developed at the project definition stage, and must be shared with the Procurement Unit.

The requisitioner is responsible for developing the Requisition Plan, including the following minimum information:

  • Description of goods, services or works
  • Quantities
  • Estimated budget
  • Expected completion date of activity

Low-priority procurement categories can be quantified and budgeted in the Requisition Plan as a lump sum. For example, “stationary lot” (pens, pencils, pad, other) – QTY 1 – Budget 2,000 USD

High/medium priority procurement categories should be carefully quantified and accurately budgeted.

The Requisition Plan is based on estimates of procurement operations to be carried out.  While some procurement needs cannot be anticipated, a Requisition Plan based on estimates is always better than no planning at all.

SUPPLY CHAIN MANAGEMENT PLAN

At the planning stage, it is always necessary to take into consideration the entire SCM, including the project requirements and UNDP’s roles and responsibilities in terms of the SCM.

However, it is only under certain circumstances, and normally due to the extension and complexity of the SCM, that the Country Office or Business Unit will need to develop a SCM Plan in writing.

For some projects with an extended and complex SCM, we recommend the development of a SCM Plan before moving into the development of the transactional Procurement Plan. An example of such a project is voter registration support or electoral assistance support, in which the quantification process, logistics, storage, transportation and distribution are highly demanding and critical for the overall project success.

In these cases, it is important to analyze each step of the SCM, identify roles, responsibilities, existing infrastructures, potential bottlenecks and actions to be taken.

Examples include:

  • Inventory management
    • Is sufficient storage space available at all level of the distribution chain (central/regional/ district)?
    • Provide estimates of the total storage space that exist. If there is no sufficient space indicate alternative solution.
    • Are there any items that require special storage conditions?
    • What are the security conditions? How would sensitive items be treated?
    • Who is responsible for coverage against theft, damage, etc.?
    • Does any inventory management system exist?
    • Does there exist a clear process and procedure for the receipt of goods?
  • Distribution
    • To approximately how many points are products distributed? Distinguish between distribution points; for example, central storage, regional, and site storage.
    • Are there any significant challenges in distributing to the sites (e.g. lack of roads, conflict zones, very long distances, seasonal rains, etc.)?
    • What are the estimated distribution lead times from central to regional locations (each) and from regional locations to sites (each)?
    • Will a pull or push system be used?
    • Who is responsible for the risks encountered during distribution? If UNDP, does insurance exist?

TRANSACTIONAL PROCUREMENT PLAN

Based on the received Requisition Plan and after taking into consideration the market situation and associated risks, proceed to developing a Procurement Plan.

All Requisition Plans for significant procurement shall be converted to a Procurement Plan.

When developing Consolidated or Individual Procurement Plans, it is important to take into consideration any existing long-term or other arrangements. The minimum information included in the Procurement Plan should be:

  • Type of goods/services/works to be provided
  • Method of procurement
  • Estimated cost (unitary and total)
  • Expected date for specification/TOR/SOW to be finalized
  • Sourcing period
  • Bidding period
  • Evaluation period
  • Award (CAP or ACP if applicable)
  • Delivery time

Go to top

5.0 Inputs


N/A

Go to top

6.0 Deliverables


N/A

Go to top

7.0 Roles and Responsibilities


N/A