1.0 Description
Procurement is an important function to ensure that UNDP meets its organizational goals. While Procurement is a support
function for the organization, it is nevertheless a core function and critical to enhancing programme/project delivery. UNDP
does not conduct procurement in isolation, but rather as part of the process of achieving development project outcomes. Therefore
all UNDP procurement activities are framed in the context of UNDP programmes and projects.
Understanding procurement as a managerial
discipline (and not an administrative one) implies the need to acquire and enhance certain managerial skills and
tools, including: - Procurement Risk Management
- Procurement Strategies Development
- Procurement Planning
|
Understanding…
What do we procure? (Spend
Analysis) | In which markets do we operate? (Market Analysis) | What are the associated risks? (External, internal, project risks) |
We
will develop…
| Risk Procurement Management | Procurement Strategies | Procurement
Plans |
When we talk about procurement, is it necessary to broaden the concept to include Supply
Chain Management (SCM), as procurement is one of the elements of the Supply Chain.
Management of the supply chain
also includes:
- Product selection
- Forecasting or quantification
- Procurement, including Quality Assurance
- Inventory
management, including Storage (if applicable)
- Distribution (if applicable)
- Return (if applicable)
As
a working principle, we always need to take into consideration all steps of Supply Chain Management (SCM) when analyzing procurement
risks, defining procurement strategies and planning. The complexity and length of the supply chain will vary from project
to project.
Supply Chain Management risk analysis, procurement strategies development and planning are essential tools
to ensure that procurement activities support project outcomes, are conducted in a timely manner and at a
reasonable cost. Early and accurate planning is critical to avoid last minute procurement, which is contrary to open, efficient
and effective procurement.
When does (1) procurement risk analysis (2) procurement strategies and (3) procurement
planning start?
SCM cycle is an integrated part of the project cycle, and therefore needs to be aligned
and synchronized with other project activities in order to contribute to achieving identified outcomes. To this end, the SCM
cycle cannot run in isolation. On the contrary, it must be integrated into the overall project cycle.
This implies by
definition the need for a constant interaction between operations and programming.
| In the project context, SCM risk assessment
and procurement strategies development and planning should start as early as the project definition stage. |
At
this point, important questions will need to be addressed, including:
- What will be the implementing modality? Who
will be responsible for procuring and managing inputs?
- What are the existing risks? Are there risks associated with
the nature of the
- products or services to be acquired? Are risks associated with the markets, the environment or
the political context?
- What is the best procurement strategy for achieving the programme/project goals and to mitigate
risk?
- What is the Procurement Plan and what are the associated resources?
- What are the main acquisition activities
to be conducted that will contribute to the identification of project outputs? Among these activities, will there be acquisition
of goods, services (professional or individual) or works?
- What is the procurement and product expertise required to
successfully conduct the identified procurement activities? Does it exist in house or do we need to outsource it? Does UNDP
or the implementing partner have the capacity to develop specifications/TOR/SOW, or do we need to hire specialized experts?
What about the evaluation?
- What is the budget required to achieve the identified outcomes? All required activities,
either goods to be procured (i.e., ballot boxes for an electoral project) or services (i.e., individual consultants to develop
specifications) must be budgeted.
What are the benefits of this approach?
Together,
procurement risk assessment, procurement strategies development and procurement planning serve as a bridge to cover the gap
between programme and operations. They are also critical to programme delivery. Benefits of this approach include:
- Best
value for money
- Timely procurement
- Avoid unnecessary and unjustifiable emergencies
- Better allocation
of existing resources
- Sufficient time to fully explore alternative procurement approaches
- Possibility to aggregate
demand
What are the success criteria?
- Joint Planning between programme and
procurement in the early stages
- Good flow of communication
- Understanding of the procurement requirements
- Understanding
of the market and associated risks
- Live process with structured revisions and feedback mechanisms
TYPES OF PLANNING - Consolidated
planning
- Individual planning
Consolidated Planning Based on the UNDP decentralized
structure, consolidated procurement plans will be developed at different levels, including Corporate, Business Unit and Country
Office. All Business Units and Country Offices shall develop Consolidated Plans. They will normally
be prepared annually, though it is a good practice to review them regularly. Analysis of the consolidated Procurement
Plan provides an opportunity to identify economies of scale and better uses of resources, providing an overview of the scale
of the procurement activities. Individual planning Procurement planning will also take
place at the project level or even at the activity level, depending on the complexity of the activity and the number of interrelated
procurement actions. A Requisition Plan shall be developed at the project definition stage. It must be shared
with the Procurement Unit. All “Significant Purchases” of a Requisition Plan (definition is provided in
Section 4.2) are subject to the development of an Individual Procurement Plan. |
Go to top
2.0 Relevant Policies
- UNDP Fin. Rule 121.03(a) (May 2005)
Go to top
3.0 Flow Chart
There is no flowchart for this sub-process
Go to top
4.0 Procedures
As SCM (and procurement in general) is a sub-process of the project cycle, different actions will need to be taken at each
stage of this cycle.
The UNDP Project Management Cycle includes the following steps:
- Justifying
the project
- Defining the project
- Initiating the project
- Running the project
- Closing the project
Below
are some of the questions and issues that must be considered at different stages of the project.
| Project Cycle | Procurement
Cycle/SCM | Main Documents |
| Justifying a project | N/A | N/A |
| Defining
a project | - Identify internal procurement resources
- Identify external resources (if required)
- Identify
procurement risks and procurement strategies
- Product/service selection or identification
- Forecasting/Quantification
- Budget
- Identify
SCM responsibilities
- Assess SCM implementing partner capacities
- Develop REQUISITION PLAN
- Identify
asset management strategy
| PRODOC PROCUREMENT RISK ASSESSMENT PROCUREMENT STRATEGIES (including
sourcing strategies) REQUISITION PLAN SUPPLY CHAIN MANAGEMENT PLAN (if applicable) |
| Initiating
a project | - Development of a TRANSACTIONAL PROCUREMENT PLAN
- Develop Specifications/ TOR/SOW
| TRANSACTIONAL
PROCUREMENT PLAN |
| Running a project | - Monitor and review Procurement Plan or the Procurement
and Supply Management Plan
- Source Suppliers
- Select Suppliers
- Award and Contracting
- Monitor
performance and manage contracts
- Depending on the SCM obligations indentified during the definition of the project,
UNDP will be responsible for storage, inventory management and distribution
| MONITORING AND ADJUSTMENT OF
THE TRANSACTIONAL PROCUREMENT PLAN/SUPPLY CHAIN MANAGEMENT PLAN |
| Closing a project | - Close
project
- Dispose/transfer assets
- Identify procurement lessons learned
| . |
Procurement
Risk Assessment, Procurement Strategies Definition and Planning shall be integrated at the programming stage and
not as a back-end process.
4.1 PROCUREMENT RISK ASSESSMENT AND RISK MANAGEMENT
UNDP needs
to proactively and systematically monitor and manage risks (defined as both threats and opportunities). Among
other risks, UNDP must identify and manage any risks associated with the conduct of its procurement activities. UNDP must
not only be aware of and monitor the procurement risks it faces, but it must also proactively anticipate and assess those
risks. This chapter deals exclusively with “transactional” procurement risks. Therefore it does not elaborate on Corporate
Procurement risks, which are part of UNDP Corporate Procurement Strategies.
UNDP has adopted an Enterprise Risk Management
strategy which provides the frame to deal with all risks, including procurement risks. For further information about ERM at
The
Risk Management Cycle includes the following steps:
| 1. Risk
Identification | What are the key risks and opportunities? |
| 2. Risk Assessment | How does the
potential impact relate to our risk tolerance? What is the likelihood of a risk event and what would be the impact? |
| 3. Risk
Prioritization | What are the most critical risk issues that demand our attention? |
| 4. Taking Action | What
is the best course of action? What are our strategies? How will we know that our mitigating actions are effective? |
| 5. Monitoring
and Reporting | Are action plans being implemented? Are they effective in mitigating risk? How are we monitoring their
implementation? |
A number of procurement risks must be taken into consideration when defining procurement strategies.
These can be clustered in three main groups: - Environmental risk, including the political environment,
natural environment or delivery infrastructure environment, among others
- Programme risk, including but not
limited to the risk of operating in the market, the complexity of the Supply Chain Management, or the risk associated with
the nature of the service or goods to be acquired, among others
- Implementation risk, or risk associated with
the implementation unit capacity
|
In the table below you will find some examples
of potential risks and mitigation activities. Please note that this list is for reference purposes only and is not exhaustive.
| Risk | Possible
Consequences | Possible Solutions |
| Critical procurement activity | | |
Failure
to secure ongoing supply critical to the organization (i.e., elections) | Failure to achieve key organizational
results Total costs of procurement too high | Develop market knowledge Identify alternative sources
and extra due diligences to check he capacity of suppliers Plan in advanced Work closely with beneficiary/ partner
to be aware of rapid changes of needs Apply contractual penalties and remedies |
| Selection
of procurement Strategy | | |
| Selection of inappropriate procurement strategy | Inadequate
or inappropriate results Not achieving best value for money Damage project implementation | Agree
on desired outcomes/objectives and have a clear understanding of the project objectives Develop a good understanding
of associated risks in order to incorporate them into procurement strategies development |
| Planning | | |
| Lack
of planning | Delay in project implementation Inadequate supplier response Procurement process shortcuts Higher
prices | Early involvement of procurement officers in project planning Develop and communicate an accurate
Requisition Plan |
| Insufficient lead-time | Inadequate supplier response Procurement process
shortcuts Higher prices | Involve procurement officers in the project planning phase |
| Delay
requisitions to create false emergencies | Claims of unethical or unfair dealings Delay of project implementation Higher
total cost of acquisition Not achieving Best Value for Money | Early involvement of procurement officers
in project implementation Seek proper justification of emergencies Training of requisitioners |
| Requirements
definition | | |
| Restrictive specifications/TOR/SOW | Claims of unethical or
unfair dealings Inadequate suppliers response Limits competition Unfair treatment of suppliers Lack
of transparency | Developed market and product understanding Include generic functional and performance
specifications Apply relevant international standards where applicable |
| Inadequate specifications/TOR/SOW | Significant
variety in offers received Insufficient responses Offer of goods/services that do not meet needs Difficulty
in evaluating competing offers | Become familiar with requirements of the specification/TOR/SOW Developed
market and product understanding External support (consultant) to developed specifications/TOR/ SOW linked to clear
deliverables and target time |
| Do not include quality requirements in specifications/TOR/SOW | Impossibility
to achieve best value for money Difficulty in comparison and overall evaluation Poor quality of the procured items,
which may lead to a waste of funds | Include quality in the specifications/TOR/SOW, using international and
national standards If quality is a critical issue, extra due diligence must be used (i.e., check manufacturing process
and standards, factory visits, sampling and independent laboratory analysis, pre-shipment inspection, etc.) |
| Sourcing | | |
| Wrong
approach to market | Inadequate or inappropriate supplier response Higher prices Selection of inappropriate
approach | Analyze supply market Develop sourcing strategies |
| Identify wrong sourcing
strategy or do not have sourcing strategy | Inadequate or inappropriate supplier response Limit competition | Proper
application of the pre-qualification or post-qualification, depending on the identified complexity and risk |
| Misrepresentation
of facts by potential suppliers | Contract with unsuitable companies Claims of unethical or unfair dealing Breach
of contract | Independently verify suppliers’ qualifications Conduct supplier reference check and due diligences |
| Outdated
information on potential suppliers | Inadequate suppliers response Limit competition | Maintain suppliers
roster |
| Advertisement of procurement notices in inappropriate media | Lack of sourcing strategy Limit
competition Contract with unsuitable companies | Identify relevant media to post procurement notices |
| Preparation
and issuance of solicitation documents | | |
| Use of inappropriate evaluation criteria | Inadequate
or inappropriate results Not achieving best value for money Re-tendering (time/ cost) | Have clear
goal to be achieved as a result of the procurement process Consider implications of evaluation criteria |
| Unacceptable
requirements to suppliers | Loading the cost in offers Limits competition Too few bids Re-tendering
(time/cost) | Develop strong understanding of market and industry practices Develop commercially acceptable
terms Check that responsibility for risks is not allocated to suppliers for factors outside their control |
| Provisions
of inadequate information | Loading cost in offers Great variation in offers Create confusion among potential
suppliers Re-tendering (time/cost) | Review documents before issue Know the market |
| Receipt
and Evaluation | | |
| Failure to observe effective evaluation procedures | Lack
of fair treatment of suppliers Inconsistency in evaluation of offers Subjectivity in outcome of the evaluations | Composition
of the evaluation team in line with the project scope and complexities For high tech/highly complex procurement activities,
ensure technical expertise Ensure staff are suitably trained and experienced |
| Failure of offers
to meet project needs | Need to re-tender | Ensure that specifications are understandable, generic, and in
line with what exists in the market Know the marketplace |
| Failure of evaluation to identify a clear
winner, leading to subjective discussions or development of “new criteria” | Claims of unethical and unfair behavior Need
to re-tender | Ensure that selection criteria are appropriate and aligned with the project needs |
| Selection
of inappropriate supplier | Failure of the supplier to fulfill the contract Waste of funds Contract disputes Re-tendering
(time/cost) | Reject offers from unacceptable suppliers and document rationale for the rejection Develop
clear evaluation criteria aligned with the project needs Perform technical and financial checks on suppliers before
awarding the contract |
| Select inappropriate goods/ service | Failure of goods/services to meet
the project needs Waste of funds Re-tendering (time/cost) | Develop proper specifications/ TOR/SOW Have
the right technical expertise during the evaluation process Ensure users are involved |
| Insufficient
number of responses | Need to start the procurement again Delays to procurement schedule Lack of value
for money due to limited competition | Develop strong understanding of market Foster international competition Develop
supplier rosters Allow for sufficient time for suppliers to prepare offers |
| Procurement
Review and Award | | |
| Contract approval not obtained | Delay in the contract
award Need to re-bid (time/cost) Undermine business community trust | Proper procurement risk analysis Proper
procurement strategies (including sourcing strategies) Market understanding Proper procurement planning Clear,
generic and complete specifications/TOR/ SOW Foster international competition Ensure adherence throughout process
to rules, regulations and procedures Ensure adequate documentation of process and submission |
| Contract
management | | |
| Unstructured or nonexistent contract management function | Not
achieving best value for money Poor performance of suppliers Delivery delays Possible cost variation Contract
disputes | Identify resources for contract managements Develop structures for contract management, including
clear roles and responsibilities Identify the right profile and competences for contract management Develop contract
management plans |
| Failure by either party to fulfill the conditions of the contract | Contract
disputes Failure or partial failure to satisfy the project needs Delays Legal actions | Ensure
proper contract management Contract monitoring, including regular inspections and progress reports Review past
performance records Be proactive Maintain accurate records and documentations |
4.2
DEFINITION OF TRANSACTIONAL PROCUREMENT STRATEGIES
First and foremost, any procurement activity needs
to be aligned with the UNDP Strategic Plan. Please familiarize yourself with the Strategic Plan by visiting http://intra.undp.org/results/strategic_plan.shtml.
Based
on the information gathered, potential buying strategies should be identified and evaluated.
All procurement activities require procurement
strategies. However, activities designated as “significant purchases” will require special attention. We can define
significant purchases as those that are of high relative expenditure and/or for which supply is difficult
to secure. |
The relative expenditure of goods and services is defined as their
cost relative to the total purchasing expenditure of the business unit or agency. For UNDP, a transaction of 100,000
USD or more is considered a significant purchase.
The criterion “difficult to secure supply” will
be based on the following factors:
- The degree to which the goods or services being purchased present a risk or
are critical to the agency; as well as
- The extent to which there exists a competitive market

Significant purchases are:
- High
in relative expenditure and easy to ensure supply
- Low in relative expenditure and difficult to secure supply; and
- High
in relative expenditure and difficult to secure supply
Based on the information gathered, an understanding of
the nature of the procurement activities, a knowledge of the market and an understanding of existing risks, UNDP will develop
unique procurement strategies for each project. Potential strategies include:
- A purchase high in relative
expenditure and easy to ensure supply may require a strategy with the aim to ensure that total cost (including the cost of
processing large numbers of low value transactions) are reduced (i.e., demand aggregation).
- A purchase low in relative
expenditure and difficult to secure supply may require a strategy seeking to ensure an ongoing supply, in order to reduce
exposure (i.e., carrying an emergency stock or developing alternative sources of supply).
- A purchase high in relative
expenditure and difficult to secure supply may require special supplier relationship management.
Procurement strategies
will seek to meet identified project goals and to mitigate existing risks. For example, in the case of a procurement transaction
where quality is critical, UNDP procurement strategies will not only include clear specifications reflecting national and
international standards, but could also include supplier pre-qualifications, factory visit(s), sampling and independent laboratory
testing, or pre-shipment inspection, among other actions.
In the case of a project were delivery is critical (i.e.,
elections), potential strategies could include early ordering (if proper planning has been conducted), pre-qualification of
suppliers (to ensure that with all suppliers being considered are reputable and capable), developing alternative sources,
checking manufacturing capacity, requesting performance security and including extra assurances in the contract as liquidate
damages clauses, among others.
4.3 PROCUREMENT PLANNING
Procurement planning entails more than
the selection of a procurement method for various goods, civil works and services or when to schedule activities. It is highly
dependent the legal and institutional frameworks in which procurement must be carried out.
REQUISTION PLAN
During
the definition stage of the project cycle, all relevant activities will need to be identified and budgeted. Among these activities,
considerations must be taken for the acquisition of goods, services and works in order to achieve the project objectives.
Required services identified should also include any individual consultant services necessary for the successful implementation
of the project (including services for complex/highly technical specifications development, if applicable). This information
will be the groundwork for the establishment of the Requisition Plan.
The Requisition Plan shall be developed at the project definition stage,
and must be shared with the Procurement Unit. The requisitioner is responsible for developing the Requisition Plan,
including the following minimum information: - Description of goods, services or works
- Quantities
- Estimated
budget
- Expected completion date of activity
|
Low-priority procurement
categories can be quantified and budgeted in the Requisition Plan as a lump sum. For example, “stationary lot” (pens,
pencils, pad, other) – QTY 1 – Budget 2,000 USD
High/medium priority procurement categories should
be carefully quantified and accurately budgeted.
The Requisition Plan is based on estimates of procurement operations
to be carried out. While some procurement needs cannot be anticipated, a Requisition Plan based on estimates is always
better than no planning at all.
SUPPLY CHAIN MANAGEMENT PLAN
At the planning stage, it is
always necessary to take into consideration the entire SCM, including the project requirements and UNDP’s roles and responsibilities
in terms of the SCM.
However, it is only under certain circumstances, and normally due to the extension and complexity
of the SCM, that the Country Office or Business Unit will need to develop a SCM Plan in writing.
For some projects with
an extended and complex SCM, we recommend the development of a SCM Plan before moving into the development of the transactional
Procurement Plan. An example of such a project is voter registration support or electoral assistance support, in which the
quantification process, logistics, storage, transportation and distribution are highly demanding and critical for the overall
project success.
In these cases, it is important to analyze each step of the SCM, identify roles, responsibilities,
existing infrastructures, potential bottlenecks and actions to be taken.
Examples include:
- Inventory management
- Is
sufficient storage space available at all level of the distribution chain (central/regional/ district)?
- Provide estimates
of the total storage space that exist. If there is no sufficient space indicate alternative solution.
- Are there any
items that require special storage conditions?
- What are the security conditions? How would sensitive items be treated?
- Who
is responsible for coverage against theft, damage, etc.?
- Does any inventory management system exist?
- Does
there exist a clear process and procedure for the receipt of goods?
- Distribution
- To approximately
how many points are products distributed? Distinguish between distribution points; for example, central storage, regional,
and site storage.
- Are there any significant challenges in distributing to the sites (e.g. lack of roads, conflict
zones, very long distances, seasonal rains, etc.)?
- What are the estimated distribution lead times from central to
regional locations (each) and from regional locations to sites (each)?
- Will a pull or push system be used?
- Who
is responsible for the risks encountered during distribution? If UNDP, does insurance exist?
TRANSACTIONAL
PROCUREMENT PLAN
Based on the received Requisition Plan and after taking into consideration the market situation
and associated risks, proceed to developing a Procurement Plan.
All Requisition Plans for significant procurement shall
be converted to a Procurement Plan. When developing Consolidated or Individual Procurement Plans, it is important
to take into consideration any existing long-term or other arrangements. The minimum information included in the Procurement
Plan should be: - Type of goods/services/works to be provided
- Method of procurement
- Estimated cost
(unitary and total)
- Expected date for specification/TOR/SOW to be finalized
- Sourcing period
- Bidding
period
- Evaluation period
- Award (CAP or ACP if applicable)
- Delivery time
|
Go to top
5.0 Inputs
N/A
Go to top
6.0 Deliverables
N/A
Go to top
7.0 Roles and Responsibilities